SC Air Power Tech logo

Filtration and Dewatering - Customer-site case study

TF273L dry screw vacuum pump for ore dewatering

An ore company in Tangshan, Hebei, China tested TF273L as the dry screw vacuum pump reference for an ore dewatering line. The work started with an energy-saving request and became a customer-site test around wet carryover, non-corrosive liquid, and actual production-line vacuum demand.

TF273L dry screw vacuum pump installed at an ore-company customer site in Tangshan, Hebei, China for dewatering duty

Operating point

210 m3/min

customer required volumetric flow rate at 25000 Pa(a)

Location

Tangshan, Hebei, China

Model reference

TF273L dry screw vacuum pump

Previous pump

2BEC-42 water ring vacuum pump

Site test result

One TF273L supported three production lines

Project background

The project began with a power-consumption target. An ore company in Hebei wanted its dewatering line to use less electricity as China moved further toward carbon neutrality. SC Air Power Tech then proposed a joint test with the disc dewatering equipment manufacturer that supplied the line.

Vacuum duty in the process

On this dewatering line, the vacuum pump is not only used for a short drawdown. After loading, the process has to keep its working vacuum until the next loading step. The same vacuum also pulls liquid through the filter media, so the pump package has to be reviewed around moisture, liquid carryover, and any solids that may be carried with it. This is the same application direction covered on our filtration and dewatering vacuum pump page.

1

Stable holding vacuum

After loading, the dewatering line has to hold its working vacuum steady until the next loading step.

2

Wet carryover

Liquid carryover was expected on the vacuum side. For this project, the liquid was checked before testing and confirmed as non-corrosive.

3

Solids protection

Solid particles could move with the wet carryover, so the package used a gas-liquid separator and an inlet filter before the pump chamber.

Existing system challenge

The original process used a 2BEC-42 water ring vacuum pump. During earlier cooperation with other dry screw vacuum pump suppliers, the dewatering equipment manufacturer kept running into the same limitation: those pumps were not intended to accept liquid entering the pump chamber. SC approached the duty differently. We reviewed the pump package for wet carryover into the working chamber, after checking the liquid condition and protection details.

For this project, the carried liquid was confirmed as non-corrosive. With that point settled, TF273L could be installed at the ore site for the dewatering test.

SC test setup

TF273L was used as the test model. The customer required operating point was 210 m3/min at 25000 Pa(a). Before the test, the disc dewatering equipment manufacturer expected one TF273L to support one production line, based on calculations from the previous water ring pump parameters.

Model referenceTF273L
Customer required operating point210 m3/min at 25000 Pa(a)
ApplicationOre filtration and dewatering
Previous pump2BEC-42 water ring vacuum pump
Liquid conditionLiquid carryover reviewed and confirmed as non-corrosive for this project
Configuration reviewWet carryover into the working chamber, separator layout, inlet filtration, drainage, leakage, and operating duty
Customer-site testing video of the TF273L pump package in the ore dewatering area.

Verified result

The site test changed the sizing discussion. The original estimate was higher than the actual vacuum demand, and one TF273L dry screw vacuum pump supported three production lines. With all three lines connected, the measured power consumption was 120 kW.

For comparison, the previous 2BEC-42 water ring vacuum pump required 160 kW to support one production line. The figures gave the customer a practical energy comparison for this plant and helped frame later expansion planning.

Tested SC setupOne TF273L supporting three production lines
TF273L power consumption120 kW with three production lines connected
Previous water ring setupOne 2BEC-42 water ring vacuum pump supporting one production line
Previous power consumption160 kW for one production line
One-month customer reportApproximately 60% reduction in power consumption compared with the previous water ring vacuum pump system
Customer savings estimateApproximately RMB 400,000 in the first year after procurement cost, then about RMB 970,000 per year

What this test changed in the review

This project changed two parts of the review. First, the existing water ring pump data gave a conservative starting point, but the site load still had to be checked under production conditions. Second, wet carryover could be accepted only after the liquid condition, gas-liquid separator, inlet filter, and drainage details were reviewed together.

Need a dewatering vacuum pump review?

Send the working pressure and required volumetric flow rate first. Current pump model, site photos, liquid condition, and inlet protection details can be confirmed during follow-up.

Inquiry Now