Project Overview
In late 2025, we were contacted by a large iron ore processing plant in Hebei that was expanding its production capacity with a new disc filter system for dewatering. Their existing vacuum setup had been running for years, but with the new line coming online, the problems they had been tolerating could no longer be carried forward.
The existing vacuum system consisted of:
- 2 × Water Ring Vacuum Pumps (2BEC-42)
- Total installed power: 400 kW
- Required operating vacuum: -70 kPa
Client Challenges
Our initial site assessment identified four issues that had been compounding over time:
- Unstable vacuum: Levels fluctuated between -40 kPa and -60 kPa, well below the required -70 kPa. Filter cake moisture exceeded 22%, creating inconsistency in downstream processing.
- High energy consumption: Two pumps running in parallel at a combined 400 kW for a system that should have required far less.
- High water consumption: Continuous water circulation was required, adding treatment costs on top of raw usage.
- Escalating maintenance costs: Impellers and distributors needed replacement every 3 months. The water circuit added regular descaling and chemical treatment on top of that.
With stricter uptime requirements tied to the new disc filter line — continuous runs of up to 168 hours, annual availability of ≥ 8,000 hours, and planned downtime capped at ≤ 24 hours per year — a patch job wasn’t an option. The system needed to be replaced.